Final Walkthrough Checklist (Substantial Completion)

Substantial completion is the legal milestone where the owner can occupy the project for its intended use. The final walkthrough either generates a clean punchlist (project closes) or a fight (project drags into liquidated damages). This checklist surfaces the items inspectors and architects actually flag — not the obvious ones, but the corners that get missed.

References: AIA G704 Certificate of Substantial Completion, AIA G714

015 items

Pre-walkthrough Setup

  1. 01
    Project clean — all trash, debris, packaging removed
  2. 02
    All trades complete (no active work during walkthrough)
  3. 03
    Power, water, HVAC operational throughout building
  4. 04
    All lighting on for inspection (replace failed lamps before walk)
  5. 05
    Owner punch person + GC superintendent present

025 items

Building Envelope

  1. 06
    No water staining at ceiling penetrations (HVAC, sprinkler, plumbing)
  2. 07
    Caulk joints continuous at all envelope penetrations
  3. 08
    Roof drains free of debris, scuppers clear
  4. 09
    Window/door operation smooth, weatherstripping intact
  5. 10
    Exterior signage installed level, illuminated if applicable

035 items

Life-Safety Systems

  1. 11
    Fire alarm functional — pull stations, horns, strobes test
  2. 12
    Sprinkler system flushed, gauges normal, signage posted
  3. 13
    Emergency lighting and exit signs illuminated, battery test passed
  4. 14
    Egress paths clear, exit doors open with single motion

    IBC 1010

  5. 15
    Elevator inspection certificate posted, recall test passed

044 items

Mechanical / Electrical Test

  1. 16
    HVAC balancing report on file, all zones at design temp
  2. 17
    Electrical panel schedules typed and accurate
  3. 18
    Receptacles polarity-tested, GFCI/AFCI trip tested at samples
  4. 19
    Plumbing fixtures tested for flow + drain, no cross-connections

054 items

Closeout Documentation

  1. 20
    O&M manuals delivered (3 copies + digital)
  2. 21
    Warranty letters signed and dated by each subcontractor
  3. 22
    Attic stock (paint, tile, ceiling tiles, lamps) delivered to owner
  4. 23
    As-built drawings and final permits in handoff binder