Final Walkthrough Checklist (Substantial Completion)
Substantial completion is the legal milestone where the owner can occupy the project for its intended use. The final walkthrough either generates a clean punchlist (project closes) or a fight (project drags into liquidated damages). This checklist surfaces the items inspectors and architects actually flag — not the obvious ones, but the corners that get missed.
References: AIA G704 Certificate of Substantial Completion, AIA G714
015 items
Pre-walkthrough Setup
- 01Project clean — all trash, debris, packaging removed
- 02All trades complete (no active work during walkthrough)
- 03Power, water, HVAC operational throughout building
- 04All lighting on for inspection (replace failed lamps before walk)
- 05Owner punch person + GC superintendent present
025 items
Building Envelope
- 06No water staining at ceiling penetrations (HVAC, sprinkler, plumbing)
- 07Caulk joints continuous at all envelope penetrations
- 08Roof drains free of debris, scuppers clear
- 09Window/door operation smooth, weatherstripping intact
- 10Exterior signage installed level, illuminated if applicable
035 items
Life-Safety Systems
- 11Fire alarm functional — pull stations, horns, strobes test
- 12Sprinkler system flushed, gauges normal, signage posted
- 13Emergency lighting and exit signs illuminated, battery test passed
- 14Egress paths clear, exit doors open with single motion
IBC 1010
- 15Elevator inspection certificate posted, recall test passed
044 items
Mechanical / Electrical Test
- 16HVAC balancing report on file, all zones at design temp
- 17Electrical panel schedules typed and accurate
- 18Receptacles polarity-tested, GFCI/AFCI trip tested at samples
- 19Plumbing fixtures tested for flow + drain, no cross-connections
054 items
Closeout Documentation
- 20O&M manuals delivered (3 copies + digital)
- 21Warranty letters signed and dated by each subcontractor
- 22Attic stock (paint, tile, ceiling tiles, lamps) delivered to owner
- 23As-built drawings and final permits in handoff binder
OnsiteAudit for iPhone
Run this on your phone.
Run this checklist on every site, capture defect photos as you go and build the report on site, with the AI running on the iPhone itself.
More for OnsiteAudit users
- 24 items
Concrete Pour Pre-Pour Inspection Checklist
Verify everything BEFORE the truck arrives.
- 22 items
Electrical Rough-In Inspection Checklist
Catch every NEC violation before drywall closes the wall.
- 38 items
Residential Construction Punchlist Template
Every item that delays a closing — caught at substantial completion.
- 18 items
Drywall Inspection Checklist
Every drywall failure caught BEFORE finish + paint hides it.
- 20 items
Roof Inspection Checklist (Commercial + Residential)
Catch the leak point BEFORE the next storm proves it.
- 19 items
Foundation Inspection Checklist
Verify the parts that get buried — before they get buried.
- 22 items
HVAC Commissioning Checklist
The system delivers what the design said it would.
- 20 items
Plumbing Rough-In Inspection Checklist
Verify before drywall — every penetration, every slope, every test.
- 18 items
Pre-Drywall Walkthrough Template (Customer-Facing)
The walkthrough that catches "wait, where's my outlet?" before insulation closes the wall.