Electrical Rough-In Inspection Checklist

For: Electrical inspectors, EITs, GC supervisors, master electricians

Once drywall is up, every electrical violation costs 10× more to fix. This rough-in inspection covers the items inspectors actually fail jobs on — not just the obvious code references but the workmanship items (box fill, support spacing, derating) that determine whether the install will pass first time.

References: NEC 2023 / NFPA 70 · IEC 60364 (where applicable)

Want to do this on your phone — offline, with photos per item, exported as a PDF in 90 seconds?

Use OnsiteAudit — runs offline, captures photo evidence per item, exports a sharable PDF.

Get OnsiteAudit

Service & Panel

  • Service rating matches drawings (panelboard label confirms ampacity)

    NEC 230

  • Panel grounding electrode conductor (GEC) sized correctly

    NEC 250.66

  • Bonding jumpers present at metallic raceway transitions

    NEC 250.92

  • Working clearance maintained (≥30 in wide, 36 in deep, 6.5 ft high)

    NEC 110.26

  • Panel circuits labeled with permanent durable labels

    NEC 408.4

Branch Circuit Wiring

  • Conductor ampacity sized for load + derating + ambient

    NEC 310.15

  • AFCI protection on bedroom + living areas + kitchens (where required)

    NEC 210.12

  • GFCI protection at kitchen counter, bathroom, garage, outdoor, basement

    NEC 210.8

  • Tamper-resistant receptacles in dwelling units

    NEC 406.12

  • Box fill calculation verified for switch/receptacle boxes

    NEC 314.16

  • Cables stapled within 8" of box, every 4.5' along run

    NEC 334.30

Conduit / Raceway

  • EMT supported every 10 ft + within 3 ft of box

    NEC 358.30

  • Conduit fill ≤40% for >2 conductors

    NEC Ch.9 Table 1

  • Conduit bends ≤360° between pull points

  • Bushings on EMT terminations at boxes

Box Locations

  • Receptacle box height matches drawings (typ. 16" AFF center)

  • Switch box height matches drawings (typ. 48" AFF center)

  • Boxes accessible — not buried by future framing/finishes

    NEC 314.29

  • Mud rings sized for finish surface (½", ⅝" drywall, etc.)

Grounding & Sign-Off

  • Equipment grounding conductor present in every circuit

  • Ground continuity tested at panel and at sample devices

  • Photos of every panel, every J-box, every conduit penetration captured

  • Inspector sign-off with date, time, license #