22 items5 sectionsFor Electrical inspectors, EITs, GC supervisors, master electricians

Electrical Rough-In Inspection Checklist

Once drywall is up, every electrical violation costs 10× more to fix. This rough-in inspection covers the items inspectors actually fail jobs on — not just the obvious code references but the workmanship items (box fill, support spacing, derating) that determine whether the install will pass first time.

References: NEC 2023 / NFPA 70, IEC 60364 (where applicable)

015 items

Service & Panel

  1. 01
    Service rating matches drawings (panelboard label confirms ampacity)

    NEC 230

  2. 02
    Panel grounding electrode conductor (GEC) sized correctly

    NEC 250.66

  3. 03
    Bonding jumpers present at metallic raceway transitions

    NEC 250.92

  4. 04
    Working clearance maintained (≥30 in wide, 36 in deep, 6.5 ft high)

    NEC 110.26

  5. 05
    Panel circuits labeled with permanent durable labels

    NEC 408.4

026 items

Branch Circuit Wiring

  1. 06
    Conductor ampacity sized for load + derating + ambient

    NEC 310.15

  2. 07
    AFCI protection on bedroom + living areas + kitchens (where required)

    NEC 210.12

  3. 08
    GFCI protection at kitchen counter, bathroom, garage, outdoor, basement

    NEC 210.8

  4. 09
    Tamper-resistant receptacles in dwelling units

    NEC 406.12

  5. 10
    Box fill calculation verified for switch/receptacle boxes

    NEC 314.16

  6. 11
    Cables stapled within 8" of box, every 4.5' along run

    NEC 334.30

034 items

Conduit / Raceway

  1. 12
    EMT supported every 10 ft + within 3 ft of box

    NEC 358.30

  2. 13
    Conduit fill ≤40% for >2 conductors

    NEC Ch.9 Table 1

  3. 14
    Conduit bends ≤360° between pull points
  4. 15
    Bushings on EMT terminations at boxes

044 items

Box Locations

  1. 16
    Receptacle box height matches drawings (typ. 16" AFF center)
  2. 17
    Switch box height matches drawings (typ. 48" AFF center)
  3. 18
    Boxes accessible — not buried by future framing/finishes

    NEC 314.29

  4. 19
    Mud rings sized for finish surface (½", ⅝" drywall, etc.)

054 items

Grounding & Sign-Off

  1. 20
    Equipment grounding conductor present in every circuit
  2. 21
    Ground continuity tested at panel and at sample devices
  3. 22
    Photos of every panel, every J-box, every conduit penetration captured
  4. 23
    Inspector sign-off with date, time, license #