Concrete Pour Pre-Pour Inspection Checklist

Concrete is the trade with the lowest tolerance for rework. Once it sets, mistakes become demolition. This pre-pour inspection covers the items that can still be fixed with a truck on the way and the ones that absolutely must be verified before the chute drops.

References: ACI 301-20, ACI 318-19 §26, ASTM C31/C31M, ASTM C143/C143M

014 items

Documentation & Submittals

  1. 01
    Approved mix design on-site, matches structural drawings

    ACI 301 §1.6.1

  2. 02
    Concrete delivery ticket reviewed before unloading
  3. 03
    Inspector qualifications + ICC/ACI certifications verified
  4. 04
    Reinforcing steel mill certs available for spot-check

026 items

Formwork

  1. 05
    Forms plumb and level — laser/plumb-bob check at 4 corners

    Tolerances per ACI 117

  2. 06
    Form ties properly spaced, no over-stress signs at corners
  3. 07
    Forms cleaned of debris, snow, ice, standing water
  4. 08
    Bond breaker / form release applied if reusing forms
  5. 09
    Bracing adequate for hydrostatic head — calc on file for >4 ft pours
  6. 10
    Embeds (anchor bolts, sleeves, electrical PVC) at correct elevation + offset

037 items

Reinforcing Steel

  1. 11
    Bar size, spacing, count match drawings — RFI on any deviation

    ACI 318 §25

  2. 12
    Cover verified at top, bottom, sides per exposure class
  3. 13
    Lap splices meet length requirement (no shortcuts)

    ACI 318 §25.5

  4. 14
    Hooks and bends at corners present and oriented correctly
  5. 15
    Wire ties or plastic ties at intersections — no missing ties at edges
  6. 16
    Rebar free of mill scale flakes, oil, paint that breaks bond
  7. 17
    Chairs/bolsters in place — no rebar touching forms or grade

044 items

Weather & Site Conditions

  1. 18
    Air temp ≥40°F (cold weather provisions if not, ACI 306)
  2. 19
    Air temp ≤90°F (hot weather provisions if not, ACI 305)
  3. 20
    No rain forecast within 4 hours of finishing
  4. 21
    Wind speed acceptable (high winds = surface dehydration risk)

054 items

Test Specimens & Pre-Pour Sign-off

  1. 22
    Slump test cones + tamping rod + scale on-site, calibrated

    ASTM C143

  2. 23
    Cylinder molds (4×8 or 6×12) on-site, marked, capped, ready

    ASTM C31

  3. 24
    Air content meter + calibration check
  4. 25
    Inspector pre-pour sign-off captured (photo + name + time)